Maths-
General
Easy

Question

A can do a piece of work in 40 days and B in 45 days. They work together for 10 days and then B goes away. In how many days will A finish the remaining work?

hintHint:

Hint:
When two quantities of different units are compared and expressed as a ratio, it is known as Rate. For example, a car travels at a speed of 100 kilometres per hour, then it means in one hour it covers 100 kilometres.
 

The correct answer is: 21 1/9 days.


    Let’s say that the total work can be represented as W and let’s say the amount of work that A can do in one day is WA and the amount of work that B can do in one day is WB.
    Step 1 of 3:
    It is given that A can do the whole work(W) in 40 days.
    So, work done by A in one day (WA)= W over 40……(1)
    It is given that B can do the whole work(W) in 45 days.
    So, work done by B in one day (WB)= W over 45……(2)
    Step 2 of 3:
    It is given that A and B worked together for 10 days and then B goes away.
    So, work done by A and B in 10 days = WA cross times 10 + WB cross times 10
    =  W over 40cross times 10 +  W over 45 10
    17 over 36 W
    Work left for A after B goes away = W - work done by A and B in 10 days
    = W - 17 over 36 W
    19 over 36 W
    Step 3 of 3:
    From equation (1) time taken by A to complete W over 40 work = 1 day
    time taken by B to complete 19 over 36 W equals fraction numerator 1 over denominator W over 40 end fraction cross times 19 over 36 W equals 190 over 9 text  days  end text equals 21 1 over 9 text  days.  end text
    Final Answer:
    Hence, the time taken by B to complete the work after A after 2 days is 21 1 over 9days.

    Related Questions to study

    General
    Maths-

    A and B can do a piece of work in 20 days and B in 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?

    A and B can do a piece of work in 20 days and B in 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?

    Maths-General
    General
    Maths-

    Simplifyfraction numerator 1 over denominator 2 plus square root of 5 end fraction plus fraction numerator 1 over denominator square root of 5 plus square root of 6 end fraction plus fraction numerator 1 over denominator square root of 6 plus square root of 7 end fraction plus fraction numerator 1 over denominator square root of 7 plus square root of 8 end fraction

    Simplifyfraction numerator 1 over denominator 2 plus square root of 5 end fraction plus fraction numerator 1 over denominator square root of 5 plus square root of 6 end fraction plus fraction numerator 1 over denominator square root of 6 plus square root of 7 end fraction plus fraction numerator 1 over denominator square root of 7 plus square root of 8 end fraction

    Maths-General
    General
    Maths-

    A and B can finish a work in 20 days. A alone can do 1/5th of the work in 12 days. In how many days can B alone do it?

    A and B can finish a work in 20 days. A alone can do 1/5th of the work in 12 days. In how many days can B alone do it?

    Maths-General
    parallel
    General
    Maths-

    8 bags of cattle feed are needed to feed 4 cows for 2 months. How long will the same feed last to feed 6 cows?

    8 bags of cattle feed are needed to feed 4 cows for 2 months. How long will the same feed last to feed 6 cows?

    Maths-General
    General
    Maths-

    A and B can polish the floors of a building in 10 days. A alone can do ¼th of it in 12 days. In how many days can B alone polish the floor?

    A and B can polish the floors of a building in 10 days. A alone can do ¼th of it in 12 days. In how many days can B alone polish the floor?

    Maths-General
    General
    Maths-

    A, B and C can reap a field in 15 ¾ days; B, C and D in 14 days; C, D and A in 18 days; D, A and B in 21 days. In what time can A, B, C and D together reap it?

    A, B and C can reap a field in 15 ¾ days; B, C and D in 14 days; C, D and A in 18 days; D, A and B in 21 days. In what time can A, B, C and D together reap it?

    Maths-General
    parallel
    General
    Maths-

    A rope makes 260 rounds of a cylinder with a base radius 20 cm. How many times can it go round a cylinder with a base radius 26cm?

    A rope makes 260 rounds of a cylinder with a base radius 20 cm. How many times can it go round a cylinder with a base radius 26cm?

    Maths-General
    General
    Maths-

    A and B can do a piece of work in 12 days; B and C in 15 days; C and A in 20 days. How much time will A alone take to finish the work?

    A and B can do a piece of work in 12 days; B and C in 15 days; C and A in 20 days. How much time will A alone take to finish the work?

    Maths-General
    General
    Maths-

    A and B can do a piece of work in 18 days; B and C in 24 days and A and C in 36 days. In what time can they do it, all working together?

    A and B can do a piece of work in 18 days; B and C in 24 days and A and C in 36 days. In what time can they do it, all working together?

    Maths-General
    parallel
    General
    Maths-

    A, B and C working together can do a piece of work in 8 hours. A alone can do it in 20 hours and B alone can do it in 24 hours. In how many hours will C alone do the same work?

    A, B and C working together can do a piece of work in 8 hours. A alone can do it in 20 hours and B alone can do it in 24 hours. In how many hours will C alone do the same work?

    Maths-General
    General
    Maths-

    If x equals 2 plus square root of 3 find the values of x squared plus 1 over x squared

    If x equals 2 plus square root of 3 find the values of x squared plus 1 over x squared

    Maths-General
    General
    Maths-

    Approximate the following irrational numbers to the nearest whole number.square root of 18

    Approximate the following irrational numbers to the nearest whole number.square root of 18

    Maths-General
    parallel
    General
    Maths-

    Sita can finish typing a 100 page document in 9 hours, Mita in 6 hours and Rita in 12 hours. How long will they take to type a 100 page document if they work together?

    Sita can finish typing a 100 page document in 9 hours, Mita in 6 hours and Rita in 12 hours. How long will they take to type a 100 page document if they work together?

    Maths-General
    General
    Maths-

    A man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete it in 4 days?

    A man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete it in 4 days?

    Maths-General
    General
    Maths-

    A wheel that has 6 cogs is meshed with a larger wheel of 14 cogs. When the smaller wheel has made 21 revolutions, what is the number of revolutions made by the larger wheel?

    A wheel that has 6 cogs is meshed with a larger wheel of 14 cogs. When the smaller wheel has made 21 revolutions, what is the number of revolutions made by the larger wheel?

    Maths-General
    parallel

    card img

    With Turito Academy.

    card img

    With Turito Foundation.

    card img

    Get an Expert Advice From Turito.

    Turito Academy

    card img

    With Turito Academy.

    Test Prep

    card img

    With Turito Foundation.